1. | AT THE TIME OF BOOKING | 5% |
2. | GROUND FLOOR ROOF CASTING | 10% |
3. | FIRST FLOOR ROOF CASTING | 10% |
4. | SECOND FLOOR ROOF CASTING | 10% |
5. | THIRD FLOOR ROOF CASTING | 10% |
6. | FOURTH FLOOR ROOF CASTING | 10% |
7. | AFTER COMPLETION MASONARY WORK | 25% |
8. | TILES FLOORING FINISHING | 15% |
9. | AT THE TIME OF POSSESSION | 10% |